November 23 The site for the polytunnel and the new  swing set replacement.

The front of the hall and site at the back for the sensory garden.

21.3.25 Both defunct swing sets removed before ground work starts

3.4.25 Fiona and Sue receiving

a cheque from

The Budhmor Fund

15 April 25 work starts!!

Space for the polytunnel was completed after a week of digging out 200ton of rock!! Some of it was recycles to Portnalong pier to shore up the shore!

Fiona Sue and partners cleared the swing area

We had an outside tap fitted, with thanks to Conor Chambers 

By 25.4.25 the swing and outdoor seating area were ready for phase two of the project.